International

Representative Projects

Badin Block Wellsite Automation

BP Pakistan

Pakistan

Scope: Conceptual design

Responsible for conceptual design of a SCADA system to facilitate data acquisition, control, and monitoring of its oil & gas production facilities in Badin Block. Block contained the following facilities: 89 wellhead sites; 13 remote test separator sites; 42 pump sites with either relay control panels or electric controllers/ MODBUS interface; and control center master graphics interface system.

 

Bangora #1 Early Production Facility

Tullow Bangladesh Ltd.

Bangladesh

Scope: Detailed design (process, mechanical, civil, electrical), module layout, procurement, construction management, commissioning and start-up, FEED study (process review, equipment/ piping design review, control system review).

Early production facility consists of 120 mmscfd, inlet separation, 7,000 bhp compression, refrigeration, dehydration, metering, and construction of a 10" NPS export pipeline to enable extended testing of the Bangora #1 discovery well.

 

Chachar Gas Development

Tullow (Pakistan) Developments

Chachar, Pakistan

Scope: Detailed design (process, mechanical, civil, electrical), module layout, procurement, construction management, commissioning & start-up, FEED study, PMC services, inspections

Chachar Gas Field Development consists of a total of three wells for an aggregate production of 30 mmscfd. Surface facilities consist of separation, sweetening for H2S removal, dehydration, and provision for future compression.